IZ0-451 Q&A 79

You are implementing a BPEL process for your client. In the implementation scenario, the BPEL process sends a request to a service and waits until it receives a reply, or until a certain time limit is reached, which ever comes first. Which activity will be used to achieve this.

A. Pick.

B. Assign.

C. Wait.

D. While.

Answer: A

Go to HOME_PAGE

Thanks
to Srinivasulu Kummitha for sharing this.

IZ0-451 Q&A 78

Which two statements are true regarding developing SOA composite applications using Oracle jdeveloper?

A. A service component can be created only using the SOA composite editor.

B. A project development on the same SOA infrastructure must have a unique name across SOA

composite application.

C. When a service component is deleted using SOA composite editor, all references to all are

automatically deleted.

D. When you deleted a component, any WSDL imports used by that component are removed,

even if the WSDL imports are used by other component.

Answer: B,C

Go to HOME_PAGE

Thanks
to Srinivasulu Kummitha for sharing this.



IZ0-451 Q&A 77

Which two are BPEL faults?

A. Business faults.

B. Process faults.

C. Runtime faults.

D. Static faults.

E. Dynamic faults.

Answer: A,C

Go to HOME_PAGE

Thanks to Srinivasulu Kummitha for sharing this.

IZ0-451 Q&A 76

Identify two applicable examples of business rules

A. Notifications to alert interested users about a change in the state of a task during the task life cycle.

B. Business policies such as standing policies and approval matrices.

C. Computations such as discounts or premiums.

D. Activities that are required to advance the business process.

Answer: B,C

Go to HOME_PAGE